Logic and methodology would be appreciated.If 3 men can paint a box in 2 days, what part of the job can be completed by 2 men in 1 day?
You need to figure out how much of the job a man does in a day.
3 men take 2 days to finish a job. So 1 man would take 6 days. Stated another way, a man finishes 1/6 of the job each day.
If you have 2 men, then they would finish 2 * 1/6 = 1/3 of the job in a day.
The answer is 1/3 of the box.If 3 men can paint a box in 2 days, what part of the job can be completed by 2 men in 1 day?
3 men will take 2 days
--%26gt; 3 men = 2 days
1 man will take 3 times as long
--%26gt; 1 man = 2 x 3 days = 6 days
2 men will take half the time as 1 man
--%26gt; 2 men = 6 / 2 days = 3 days
2 men will take 3 days to paint the box. Therefore, considering they do the work at an even pace, after one day they would have completed one third (1/3) of the box.
one-thirds
3men, 2days= a job
3 men, 1 day = half a job鈥?
2 men, 1 day = 2 quarters(2/3) of a job of the half of a day
so overall, it would be...0.3333% or else 1/3
3 men * 2 days = six panels
3 * 2 = 6
6 = 6
1 man = 1 panel
(2 men/panels * 1 day) * X = six panels
2 panels * X = six panels
the answer is 1/3; do you see how I found it?
a third would be a reasonable answer.
3 men for two days = 6 man days.
2 men for one days = 2 man days.
6 mandays = 1 complete box
2 mandays = 1/3 of a box